The Challenge

  • I-69 Interstate 14.5-mile lane widening
  • Assess structural response to vehicle loading for performance evaluation

The I-69 Interstate, just northwest of Indianapolis, is undergoing a reconstruction and widening of both the Northbound and Southbound lanes over a 14.5 mile stretch. As part of this re-construction, 22 different pavement test sections have been instrumented to measure the performance of the various design changes in the composition of subgrade, subgrade treatment, drainage layers, and pavement layers that make up the full pavement section.

The Indiana Department of Transportation (INDOT) wants to evaluate the performance of these full test sections by measuring the structural response to pavement loading from vehicles under controlled conditions.

The Solution

Geocomp provided the instrument selection and onsite installation oversight for all of the installed pavement instrumentation for the 22 test sections. This included: 188 Geocomp Horizontal Asphalt Strain Gages to measure flexural pavement strains, 4 Geocomp Vertical Asphalt Strain Gages to measure compressive pavement strains, 48 Thermocouples to measure pavement temperature, 78 Earth Pressure Cells to measure soil pressures, 10 Embedment Strain Gages to measure flexural strain in chemically treated subgrades, and 44 Moisture Gages to measure soil moisture at subgrade interface.

All of the pavement sensors at each of the test sections were routed to a road-side Nema enclosure with terminal strips with ready connection to a portable data logger for the subsequent field testing. The INDOT has the ability to perform long-term testing comparing the performance of each of the test sections under ambient trafficking or load testing.

Services Provided

Pavement Sensors

Installation oversight of pavement sensors routed to portable data logger

Training Program

Training the client in system operation and data collection for long-term testing

Related Projects

GEOPROJECT_Crenshaw

Crenshaw Corridor

Value Delivered:

GIMS software simplifies data reporting
Mitigate risk to adjacent structures
GEOPROJECT_Regional Connector

Regional Connector

Value Delivered:

Reduce risk to general public and building owners during
construction activity
Sensor data allowed construction activity to progress
continuously without delays
GEOPROJECT_Second Ave Subway 96th Street

Second Avenue Subway 96th Street

Value Delivered:

Real-time monitoring provided an economical alternative
to manual processing
Real-time monitoring provided responsive data to address
public safety concerns