Seismic Evaluations
Advanced engineering assessments to evaluate seismic stability of CCR disposed facilities
The Tennessee Valley Authority is the largest public power utility in the United States, operating ten coal-fired power plants. In 2015, the United States Environmental Protection Agency (EPA) put into effect national regulations and requirements for the safe disposal of coal combustion residuals (CCR).
Geocomp developed and performed enhanced seismic assessments of TVA’s CCR facilities. Using best practices aimed at eliminating inherent over-conservatism in conventional methods, Geocomp demonstrated that their critical CCR disposal facilities meet the EPA requirements for seismic stability. The approach included realistic assessments of in-situ pore pressures based on field measurements with piezometer strings so that the correct effective stresses are used in analyses. This factor alone could improve seismic stability by 30% or more.