The Challenge

  • Pueblo Viejo Mine: Second largest gold deposit worldwide, with 25.3 million ounces reserves
  • Dominican Republic’s sole gold mine; once the largest in the Western Hemisphere
  • Operations halted in 1991; resumed in 2001 with site remediation and new infrastructure

The Pueblo Viejo Gold Mine, with proven and probable reserves of 25.3 million ounces, is the second largest high sulphidation gold deposit in the world. The mine is the Dominican Republic’s only gold mine and was, at one point, the Western Hemisphere’s largest and most productive gold mine. The mine had produced more than five million ounces (moz) of gold and 22 moz of silver in its operational life; however, mining operations had to be halted in 1991 due to low gold and silver prices and a lack of appropriate technology to process the ore. Tenders were invited by Dominican Government in 2001 to resume work at the abandoned mine. The project called for site remediation and construction of new infrastructure as the existing old systems were damaged.

The Solution

GeoTesting Express, Inc. (GTX) provided rapid soil testing services in support of design of dams, plant site foundations, and transmission lines. The first phase of testing was intended to assist the client with cleanup activities at the site. The second phase included the design of two main and four smaller “saddle” dams which create the El Llagal Tailings Facility (which has a storage capacity of 450 million m3). During this phase, we performed consolidation, triaxial, permeability and index testing. During the third phase, GTX performed over 1,000 index tests including grain size, Atterberg limits, moisture content and moisture-density testing with rapid turnaround time.

GTX was able to accept these samples without delay as it maintains a foreign soil entry permit with the United States Department of Agriculture (USDA) and we were able to turn the required testing around in exceptional time and provide our client with test results as promised.

Services Provided

Test Results

Test results were provided within days of receiving instructions for testing

Efficient Testing

Our ability to receive, process, and test thousands of samples at a time while maintaining the highest quality was a major advantage

Tailored Preparation

We accommodated our client by performing unique sample preparation specifically for this project

Related Projects

GTX_PROJECT_Tren Urbano

Tren Urbano Rail System

Value Delivered:

Fast turnaround, high quality results supporting timely
decision making
Supported multiple firms while retaining strict chain of
custody and data integrity
GTX_PROJECT_Sonatrach Loading Buoys

Sonatrach Loading Buoys

Value Delivered:

Fast turnaround of international samples and competitive
pricing saved clients thousands of dollars in delays
One of the only labs in the world capable of performing
the dynamic testing required
GTX_PROJECT_Isabella Dam

Isabella Dam Emergency Spillway

Value Delivered:

Ability to adapt in order to take on a large-scale project
with expedited report dates
GTX’s credentials as a USACE validated laboratory for
rock testing helped the client meet the project specifications

Ready to Speak
with our
Experts